Dhaka Sugar refinery taking shape

Dhaka Sugar refinery taking shape

BMA in charge of engineering, equipment and commissioning

Engineering, the supply of machinery and equipment, assembly supervision and commissioning: BMA is in charge of much of the work involved in the construction of the new 3,000 tpd sugar refinery for Dhaka Sugar. The roofs of the buildings are in place and the large plants have been installed – in time for the start of the rainy season in Bangladesh.

Dhaka Sugar refinery: construction in full swing

In mid-2021, BMA shipped the first items of equipment for the new Dhaka Sugar refinery from Bremen, Germany, to Bangladesh. While piping and electrical engineering work was still ongoing, assembly of the equipment started in September. Since then, construction of the new Dhaka Sugar refinery has been progressing steadily.

Dhaka Sugar refinery taking shape
Dhaka Sugar refinery taking shape

Equipment: assembly overseen by BMA site supervisor

Two raw sugar stores, the process building and another building for sugar packaging are already complete. Overseen by the BMA site supervisor, suitable foundations are cast, the individual items assembled, and the equipment arranged exactly as intended in the concept from BMA.

Installation of juice purification and filtration systems and more

In addition to equipment from BMA, operation of the refinery also requires many different components from other suppliers, ranging from pumps to heat exchangers and conveyor systems, and to complete stations. Among them juice purification and filtration, and the plant for packaging refined sugar into 50 kg bags.

All of these have by now been delivered. In the next few weeks, BMA will receive help from the other suppliers’ site supervisors, who will oversee installation and commissioning of their own systems. While one of the two new raw sugar stores serves for pre-assembly of the equipment, the other store is already filled with raw sugar.

Dhaka Sugar refinery taking shape

Dhaka Sugar refinery: roof in place

In May, rainfall in Bangladesh rises sharply. The rainy season lasts until September, and outdoor work is therefore quite difficult during this period. This is why the heavy equipment had to be installed early using large cranes, so the roofs of the refinery buildings could be put in place in time.

Thanks to the excellent collaboration between all parties, this challenging task was successfully completed.

Upload Files Drag and drop your files here or click the button to upload your files from your computer

multi file upload Drag and drop your files Max Upload: 20 MB
close image preview
image preview
Aufgabe existieren bereits für dieses element.
Write your message in the existing thread.
Here, we opened it for you.
Geschoben, um den Media Ordner.
Die Datei wurde Hinzugefügt, um die Webseite der media-Ordner, jetzt können Sie es von dort.
poweredby
hide sidebar icon
sidebar left
sidebar menu
sidebar menuThis Page
sidebar menuAll Pages
sidebar menuShow Complete Tasks
sidebar menuShow Internal Tasks
sidebar menuSort by Date
sidebar menuSort by Priority
sidebar menuSort by Status
Tasks
Pages
no task in sidebar
Add your comments
Click any part of the page to start collaborating
              Loading...
              ×
              ×
              Approve Page

              When the page is ready, click the green button to signal to the webmaster that <b>this page is approved.

              es gab einige Fehler. Bitte versuchen Sie es erneut.
              ×
              Seite Genehmigt
              Desktop Tablet Mobile
              Zurück zur Standard-Ansicht
              Sie Lief von Website-Slots

              Das ist toll!
              It means you're growing & onboarding more clients!<br>Don't let it stop you

              Es gab einige Fehler. Bitte versuchen Sie es erneut.